Click the below links to access the Global Engagement Portfolio:
» Change Management Plan released on 3 November 2020
» Change Implementation Plan released on 10 December 2020
The ANU Recovery Plan and the ANU College and Portfolio Recovery Plans released on 13 October are available here.
Feedback
If you have a question or would like to provide feedback regarding the Global Engagement Portfolio Change Implementation Plan or the Global Engagement Portfolio Recovery Plan please send your comments to org.change@anu.edu.au.
Implementation timetable
Date | Details of Consultation Process |
---|---|
3 November 2020 |
Meetings with affected staff
|
20 November 2020 |
Close of Consultation period |
3 November - 9 December 2020 | Collation of feedback from Consultation and preparation of Implementation Plan |
10 December 2020 |
Publication of Implementation Plan |
11 December 2020 | Meeting with Portfolio |
11 - 15 December 2020 | Feedback on Implementation Plan |
From 11 January 2021 | Commencement of Implementation |
Support
Staff and their family members can access free support and counselling through the Employee Assistance Program (EAP) which can be reached on 1800 808 374 (this number operates 24 hours a day, seven days a week).