Project Delivery ManualPART B REFERENCE MATERIALSECTION 4 DESIGN GUIDELINES FOR BUILDING SERVICES B4.1.1 Preamble From the commencement of project planning, all services consultants should familiarise themselves with the campus services infrastructure. Consultants should be aware of the location of all external services and make allowances for the connection to the building. The location of all services shall be shown on the appropriate design drawings. Where the project requires the relocation, modification or abandonment of services mains, then such proposals shall be clearly indicated on the design drawings. If required, the Project Coordinator will arrange meetings with the Facilities and Services Division's engineering and technical staff to discuss such matters as location and capacity of existing services. Liaison with local authorities on behalf of the University may be required. Major infrastructure mains for services such as electricity, sewer, water, natural gas, data and telephone are the property of the University. The University may engage the local service authorities to carry out any proposed augmentation or relocation works on the Universitys behalf. B4.1.2 Services Available Generally the following services are available: (a) Water supply - from city supply within the University site. Water mains pressure varies from 595 kPa to 1120 kPa. (b) Sewer - city service available. (c) Stormwater - should be assessed for capacity to carry increased loads. (d) Electricity - city supply 240 / 415 volts A.C at 50 hertz. The electrical design consultant may be required to allow for a substation to serve the building. In such an event the requirement should be discussed with the University. (e) Telecommunication services - cabling to the Universitys PABX system will have the capacity to meet the needs of the proposed building with a 50% spare capacity. (f) Computer Services - cabling to the Universitys mainframe is via a computer services network. Coordination with the Universitys IT services is required. (g) Natural Gas - from the supply within the University site. Gas pressure in the mains is approximately 200 kPa. (h) Fire Hydrant & Reticulation service - from a city supply with a water mains pressure of 850 kPa. (i) Central Building Management System. (j) Central Security Access System. (k) Irrigation. B4.1.3 Design Review During the planning phase, consultants should liaise with F&S Divisions engineering and technical staff including the Manager-University Maintenance to ensure that the Universitys requirements are addressed. Contact should be made through the nominated Project Coordinator. Before final documentation of the building services, preliminary drawings and specifications should be submitted to the Project Coordinator for review by Facilities and Services Divisions engineering and technical staff including the Manager - University Maintenance. Upon completion of documentation, one (1) copy of the drawings and specification should be provided to the Project Coordinator no less than two (2) weeks prior to inviting tenders in accordance with the following requirements: One (1) complete set of tender drawings on a 3.5"/1.44Mb computer diskette formatted to suit IBM compatible Auto Cad release 13c4 or 14. One (1) tender specification on a 3.5/1.44Mb computer diskette formatted to suit IBM compatible Word for Windows. B4.1.4 Access to Services Plant & Equipment Any new proposed mains service should be located in a manner to facilitate adequate access for the future maintenance of that service and to meet the local authority regulations and requirements. Building services should also be located to provide adequate access for maintaining the service and the equipment. Where services are located in ceiling or wall spaces, clearly defined and proper access points and paths shall be provided. Where plant or services are located in large ceiling spaces, adequate access in the form of suspended catwalks and the like shall be provided. Where plant or services are located on the roof, adequate access to the platform shall be provided in the form of catwalks and the like. Provision shall also be made for the attachment of safety harnesses in the appropriate locations (Refer B2.2.4 'Safe Working on Roofs'). B4.1.5 Permission to Excavate Under no circumstances should excavation commence before the required "Permission to Excavate" procedure is completed. The procedure involves the Facilities and Services Division's Manager, coordinating excavation clearances. However, the Project Coordinator must be consulted in the first instance. A copy of the "Permission to Excavate" form is included in Appendix B4.1. B4.1.6 Trenches New trenches excavated for the reticulation of underground services must be backfilled with controlled fill and the ground conditions restored to original condition. Monetary allowances should be made for ground restoration after trenches are backfilled. The Divisions Manager, Gardens & Grounds should be consulted via the Project Coordinator before backfilling of trenches is commenced. B4.1.7 Testing and Commissioning Of Services Contractors are required to provide the University with Inspection and Test Plans (ITP) for all commissioning procedures to demonstrate that the system operates in accordance with the Consultants design intent. The University may nominate that certain procedures are witnessed by F&S Divisions technical staff. Therefore the format of ITPs to be used shall be agreed with the University prior to preparation. All ITPs shall be submitted to and reviewed by the Consultant and F&S Divisions technical staff at least 20 working days before commencement of testing. A minimum of 48 hours notice shall be given by the Contractor for all commissioning and testing procedures to allow the Consultant and F&S Divisions technical staff to witness and sign off the procedure. Commissioning results shall be properly recorded on test result sheets and included in the O&M Manuals together with the duly completed ITPs B4.1.8 Defects Liability Period The Defects Liability Period for all building services shall be specified as 12 months from the date of Practical Completion unless otherwise instructed by or agreed with the University.
B4.1.9 Works as Executed (WAE) Drawings Within 28 days of the issuance of the Certificate of Practical Completion the contractor will provide the University with WAE drawings formatted to suit a drawing size no larger than A1. The drawings shall be provided in the following forms: One (1) set of transparencies no larger than A1 size. One (1) hard copy included in the relevant O&M Manual CAD drawings on 3.5"/1.44Mb diskette formatted to suit IBM compatible Auto Cad release 13c4 or 14. B4.1.10 Operation & Maintenance (O&M) Manuals One month prior to the programmed handover inspection a "Draft" O&M Manual shall be provided to the University for review. Within 28 days of the issuance of the certificate of practical completion, the final O&M Manual shall be provided and will include all commissioning results and WAE drawings. Three (3) copies of the final O&M manuals shall be provided to the University. Generally, the format of the manual should have an index page and include the following: (a) Cover sheet including names, addresses and telephone number of Consulting Engineer and Services Contractor. (b) Description of systems including design basis. (c) Operating instructions including Start/Stop procedures. (d) Protection and restart procedures after default. (e) Maintenance schedules, check lists and trouble shooting techniques. (f) Equipment specifications, nameplate data and suppliers. (g) Electrical controls and descriptions. (h) Manufacturers pamphlets. (i) Works-as-executed drawings including wiring diagrams for proprietary equipment. (j) Test reports as specified under Testing and Commissioning. (k) Authority approvals, equipment certificates, NOE forms etc. The Manual shall be as concise as possible, written in plain English with the descriptions referring to the relevant drawings rather than repeat information on the drawings. Manuals shall be printed in A4 format and bound in a 3 ring binder. The spine and cover should be embossed with the title of the manual as follows: THE AUSTRALIAN NATIONAL UNIVERSITY NAME OF PROJECT PROJECT DESCRIPTION Include a date on the cover of the manual. B4.2.1 Standards to Apply All electrical work shall comply with: AS3000 current edition, including the standards in Appendix A thereof; The Building Code of Australia together the ACT appendix; the ACTEW rules and regulations for ACT installations/local supply authoritys rules and regulations for installations outside the ACT and ANU OH&S codes of practice for electrical installations. B4.2.2 Main Switchboards Main switchboards shall be as defined in AS3000 Clause 0.5.85 and switchboards as per Clause 0.5.84. They shall comply with AS3000, AS3439 and the Supply Authorities requirements. All building main switchboards and boards over 200A rating shall have a minimum Form of Separation of Form 2 to AS3439.1. Switchboards shall be of the totally enclosed type, and contain a busbar assembly, separate neutral and earth bars. The switchboard shall contain 25% spare capacity. The supply to the board is 415/240 V, 3 phase, 4 wire, 50Hz MEN solidly earthed. Consultants should note the Supply Authorities minimum SC requirements for main switchboards. Switchboards shall be generally constructed in accordance with Clause B4.2.4, 'Cabinet Construction'. All busbars shall be of high conductivity copper with full size neutral identified with phase colours and arranged so as to facilitate future extensions. Boards with mains switch ratings up to 100 amp shall have insulated busbars. All switchboards shall be fitted with main switches unless otherwise specified. Control of outgoing supplies shall be as follows:800 amps CFS Unit (minimum capacity 200 amps)800 amps ACB Unit Adequate space shall be provided for: Supply authority metering equipment University BAS connections Termination of incoming and outgoing circuits University KWh check metering Future extensions or additions
All circuit breakers over 100 amps shall be labelled externally with screw on labels and smaller breakers shall be identified by an approved method. The rating of all breakers shall be indicated without removal of escutcheons or cover plates. Each switchboard shall have a label designating from where it is fed. A legend shall be fixed to the board containing circuit designations. (On main switchboards a copy of the schematic diagram shall be mounted in the switchroom.) All control wiring shall be numbered with an approved ferrule type numbering system, to conform to the numbering system on the wiring diagram. For details of labels refer to B4.2.8. 'Labelling'. B4.2.3 Distribution Boards and Control Panels Generally, cabinets shall be constructed to the standards in B4.2.4 'Cabinet Construction' and have a separate mains isolator which can be isolated without access to any live parts. The load sidewiring from the mains switch shall be connected to bus bars or active links with a separate fixing for each circuit.Boards shall comply with AS3439 and generally be of form 1 construction, and shall be accessible in terms of AS3439 (Refer 7.4.6.1). Phase conductors shall be insulated and coloured red, white and blue. LV control wiring shall be brown and ELV wiring pink. Minimum size for control wiring size shall be 1.5 sq mm stranded copper conductor. Indicator lamps shall preferably be LEDs, and any panel with lamps shall have a lamp test facility. All outgoing circuits, up to 20 amps shall exit the board via a terminal strip. All terminals shall be labelled. Each panel shall have a separate neutral and separate earth bar. The board shall contain spare space for 25% of mcbs and control gear. Normally control panels will have a SC rating of 6kA. If this rating is exceeded, fault limiting equipment shall be fitted. Outdoor equipment exposed to the weather shall have IP 56D protection. All components in the panel shall be labelled with the circuit designation and function. The board shall be fitted with a legend detailing the circuits, indicating which switchboard feeds the panel and giving the drawing number of the wiring diagram. All control wiring shall be labelled at each end and at any junction with an approved slide on ferrule system and terminated with approved lugs. For details of labels (Refer to B4.2.8. 'Labelling').
B4.2.4 Cabinet Construction This clause applies to all electrical cabinets including switchboards, distribution boards, control panels, battery charges, alarm panels etc. All cabinets shall comply with the construction requirements of AS3000 and those with a phase current greater than 100A or SC rating greater than 5kA shall comply with AS 3439 form 1 (unless otherwise specified). Cabinets shall include trim, door (unless otherwise specified) escutcheon, lock, hinges, circuit schedule, switcher and all wiring. The lock shall be compatible with the standard Lockwood cylinder so that Facilities and Services may replace it with their standard plant room lock. Cabinets shall be of the totally enclosed, metal-clad type fabricated from a minimum of 1.6mm sheet steel (except where specified otherwise) using folded sections and/or angle iron bracing where necessary for stiffeners and all joints welded with continuous seam welds. Doors shall be fitted using plated hinges, which allow the door to swing through a minimum area of 135 degrees. All wiring and circuit branches shall be behind escutcheon plates fitted with handles for easy removal. Each unit shall be of dustproof construction by using close fitting of all metal parts, approved compression gaskets, round doors and gauze screens and ventilation openings. Cabinets shall be vermin proof and still have a minimum degree of protection of IP33 unless otherwise specified. (This includes cable entries in units mounted over trenches). Cabinets for outside installation shall have IP 56D protection. Cabinets installed outdoors shall be fitted with anti-condensation heaters rated at 100 watts per cubic meter of cabinet volume. An accessible thermostat shall be provided. B4.2.5 Cables Generally all cables will be stranded copper conductors, PVC insulated 0.6 KV, V75 grade conforming to AS3147. Minimum sizes of stranded conductors to be used are as follows: Internal control cubicle wiring 1.5 sq mm Control cabling1.5 sq mmPower cabling2.5 sq mm. Wire colouring: red, white, and blue for phases & black for neutral Pink for ELV AC White for DC Black for VE Green / yellow for earth. Wiring within switchboards shall be in pvc insulated stranded copper conductors neatly arranged and wherever practicable shall be contained in capped slotted plastic ducting. The boards shall incorporate adequate space for incoming and outgoing cables and shall have facilities for cable terminations. All cabinet and small power cables shall terminate on a labelled terminal strip while larger cables shall enter and leave via appropriate cable glands. All larger cables shall be provided with suitable lugs throughout the installation the following wiring shall be adopted: Consumers Mains Pvc cable in pvc pipe, cable duct or on wiring tray. Sub-Mains Pvc cable in cable duct, conduit or on wiring tray. Sub-Circuits Pvc cable in conduit, buried in concrete slab and concealed in walls. TPS lighting circuits terminating in 3 pin sockets in the false ceiling space and wiring in the false ceiling space or in partition walls, with surface run circuits in the plant room. Cable ducts with final connections to equipment through conduit in galvanised conduit where needing mechanical protection or exposed to the weather. All wiring to fire and smoke control equipment, lifts and emergency services shall be MIMs cable or otherwise approved special cable and shall comply with Clause 2.19.7 of AS3000. All cable shall be installed in compliance with AS3013 1990 using the appropriate classification. Where communication cables are run in close proximity to mains cables they shall be insulated to a 1000v rating. Cables shall be run in configurations designed to reduce magnetic field effects. Single current carrying conductors shall be kept to a minimum. B4.2.6 Meters and Instruments When specified electricity meters shall be 'Email Polyphase Standard' type with photoelectric impulsing, 3 wire form C, voltage free contact output. When supplies have loads greater than 125 amps, the meter should have an appropriate metering class CT. Where current transformers are used for metering, the connection will be made via a 'Clipsal 1008' meter test block in accordance with drawings ANU90/E/3983 1-2 (see Appendix B4.2). Provision should be made for easy removal of the transformers. Indicating instruments shall comply with AS1042, and current transformers shall comply with AS1675.
B4.2.7 Fuses and Circuit Breakers Fuses shall comply with AS2005 (Parts 1 and 2). All fuse cartridges shall be of HRC type. Spare fuses to 10% of the number of each type of fuse used in the installation with a minimum of four (4) will be provided. All power final sub circuits, whether for lighting or power, must be protected from overload by the provision of a moulded case circuit breaker at the distribution board. Circuit breakers of the miniature moulded case type with SC rating up to 10 KA shall be used for all sub circuits and shall comply with AS3111. Two phase and three phase circuit breakers shall be of the multiple type with a common tripping device. Large frame size moulded case circuit breakers with SC rating > 10 KA shall comply with AS 2184. Rotary operating handle with door interlock facilities shall be fitted to all large frame moulded case circuit breakers. All moulded case circuit breakers shall incorporate thermal-magnetic tripping and arc extinguishing features. Shunt-trips where fitted shall be part of the circuit breaker. Low voltage air circuit breakers shall be horizontal withdrawable type, sub frame mounted, full interlocked, with main and secondary isolation contacts, runner rails and carriage gear, for cubicle mounting and shall comply with AS1930. The breakers shall be treated to withstand the rated fault current for one second and be provided with sufficient auxiliary contacts. Mcbs installed in a building shall match the existing breakers in the rest of the building. Residual Current Devices (RCDs) shall be installed to protect power outlets in the following locations: wet areas, cold rooms, workshops, laboratories, halls of residence and libraries (Refer Schematic layout in Appendix B4.3) Emergency stop buttons may be installed on laboratory power circuits where deemed desirable. Submains from the main switchboard may be protected by combination fuses switches (CFS). Combination fuse switches shall be 3 pole on-load fault making fault breaking type complying with AS1775 and housed in a separate sheet metal enclosure within the switchboard, or mounted directly onto the rising main busbar area. B4.2.8 Labelling Typed circuit schedules shall be fitted inside the doors of all switchboards behind perspex panels, and shall comprise the following: - circuit reference number; switchboard reference number; - size of cable; name of switchboard feeding the board; and - rating of circuit breaker or fuse; name of switchboard. - description of circuit; A reduced scale plan shall be installed behind a perspex cover, showing location of each light, power and switch outlet, adjacent to each distribution board. Circuit reference labels of traffolyte with black letters on a white background or of another approved non-deteriorating nature, fixed by means of screws rivets or appropriate adhesive shall identify every relay, push button, fuse circuit breaker, switch, meter, indicator light, terminal block, motor, general purpose outlet light switch and other apparatus. Where moulded plastic or bakelite switchgear is used, press-in standard markers fitted in the screw fixing recess may be used. Approved rating plates shall be fitted to each separate item of equipment. All control circuit wiring shall be labelled at each end and in junction boxes by an approved non-deteriorating means, with circuit reference numbers. All wiring shall be colour coded to maintain phase sequence identification. An approved label showing the outlet reference number shall be mounted adjacent to each lighting socket in false ceilings. B4.2.9 General Purpose Outlets General purpose outlets shall be a 10 amp capacity combination type switch and 3 pin receptacle complying with AS3131. Double outlet combinations shall be specified throughout an installation. The circuit current load shall be no more than 60% of capacity when initially installed. Weatherproof types shall be a 10 amp single pole switch and a 10 amp 3 pin receptacle mounted together in a rust proof, weatherproof housing. B4.2.10 Light Switches Light switches shall be single pole rocker action with silent operating mechanism with contacts rated at 10 amp and suitable for inductive load. B4.2.11 Clocks University practice is to install battery powered clocks. Wall clocks specified for lecture theatres shall be silent. Time clocks shall be an electronic type with a battery reserve of not less than 30 hours. B4.2.12 Commissioning and Testing All electrical installations must be tested and commissioned in accordance with the approved Inspection & Test Plans (ITP) previously submitted by the Contractor (Refer B4.1.7 'Testing & Commissioning of Services'). B4.2.13 Documentation Required Draft tender documents shall be provided to the University in accordance with Clause B4.1.3 'Design Review'. Operation and Maintenance Manuals shall be submitted to the University in a form and sequence outlined in B4.1.10 'Operation and Maintenance Manuals'. Works As Executed Drawings shall be provided to the University in accordance with the requirements of B4.1.9 'Works As Executed Drawings' B4.2.14 Supplementary Electrical Specification (SES) To aid consultants and contractors the Universitys Facilities & Services Division has produced a guide to the minimum standard of electrical work on campus. A copy of the SES is available on the Division's web page at www.anu.edu.au/facilities/. B4.3.1 Preamble The University is committed to energy reduction. Consultants are to investigate innovations which will more efficiently attain required light levels (Refer to Section B4.9 'Energy Conservation & Management'). B4.3.2 General Luminaires shall be selected for ease of lamp changing, cleaning and durability. In documenting entire floors, incorporate in the layout twenty-four hour security light fittings. Where possible, all luminaires shall be installed using the plug-in method. The entire lighting installation shall be tested for a minimum of three hours to ensure that excessive heat is not developed at fittings, accessories, terminals and switches etc. Ballasts that develop excessive noise during the defects liability period shall be replaced. B4.3.3 Compliance with the following Standards to apply
B4.3.4 Fluorescent Light Fittings Diffusers, reflectors etc shall be installed just prior to practical completion to limit dust accumulation. Reflectors to be manufactured from high quality polished aluminium with a minimum reflectance of 85%. Light fittings selected for computer laboratories or VDU applications shall be low brightness type. Switching will be arranged to provide a minimum of 50% illuminance. Prismatic diffusers shall be as follows: - K12 for public and common areas; - K19 for offices with no screen based tasks; and - K19 with silver tint for special purpose rooms. Fittings that incorporate single end PL or PLC fluorescent lamps shall not be used. Each light fitting shall be supplied with a fixed terminal block. Each terminal block shall accommodate three 2.5 mm2 cables and shall incorporate a spare 'loop' terminal. Fittings that incorporate 1200 mm long x 26 diameter fluorescent lamps are preferred. The following should be considered when selecting fluorescent light fittings: - separate ballasts shall be specified for each lamp and shall be 250 volt low loss type; - capacitors shall maintain the power factor at or better than 0.85 lagging with a rated working temperature of 38C and have a minimum clearance of 100mm from any ballast; - starter switches shall be complete with a manual reset facility and be capable of a minimum 5,000 operations; - lamp holders shall be made from non-flammable materials and shall not be combined type incorporating the starter and lampholder; - each light fitting shall be provided with a readily accessible fuse of suitable rating to isolate the fitting in the event of a fault within the light fitting; and - fluorescent lamps shall generally be 26mm diameter, 36 watt warm white, cool white or white 3500k.B4.3.5 Incandescent Light Fittings Incandescent light fittings shall be considered where no other possible applications exist. Where permitted, such light fittings shall be supplied with long life 250 volt lamps in porcelain lamp holders .
B4.3.6 Extra Low Voltage (ELV) Light Fittings Where used ELV lamps will be provided with readily accessible separate step down transformers. Traffolyte labels on the fitting and associated transformer shall be used where the transformer is remote from the light fitting. Where luminaires are recessed, fittings shall incorporate adequate provision to prevent contact with materials such as ceiling insulation. ELV dichroic halogen lamps shall have an average rated lamp life of 4,000 hours. Lamp holders shall be Bi Pin, high temperature ceramic base variety with the lamp wattage clearly identified. Where dimming of ELV lamps is required, the dimmer unit shall incorporate the following features: - soft start; - inbuilt surge protector; - internal time clock; - digital control; and - RF suppression; - halogen clean up cycle. B4.3.7 Down Lights Light fittings shall be selected which incorporate compact fluorescent or HID lamps. Incandescent lamps will not be accepted. A separate ballast shall be provided for each lamp with a suitable label identifying the lamp wattage located adjacent to the lamp holder. Ballasts shall be the switch-start type with losses after fifteen minutes no greater than 3.5 watts for 7 and 9 watt lamps and 5.5 watts for 18 watt lamps. B4.3.8 External Light Fittings Luminaires shall be selected for ease of lamp changing and cleaning. Fittings shall have adequate mechanical and electrical features to ensure durability. External light fittings shall be individually protected by HRC fuses and have adequate ventilation. Light fittings which incorporate: QI lamps, incandescent lamps and Dichroic (Halogen) ELV lamps will not be accepted. B4.3.9 Post Top Luminaires and Streetlights All post top luminaires shall be supplied by 16 mm neutral screened underground cable. Fittings shall be protected by a HRC fuse installed at the post/pole base, and accessible from the inspection plate at the base of each pole. Each post/pole shall be provided with a traffolyte label attached to the rear of the inspection plate. The neutral screen shall be connected to the body of metal posts/poles. Streetlight poles shall conform to the University standard pole - Refer to Appendix B4.4. Poles shall be rag-bolt mounted. B4.3.10 Security Lighting The provision of a safe environment, especially at night, is essential. External lighting will be designed and positioned to reduce the number of low illuminated areas adjacent to windows, doorways, pedestrian access routes and in parking areas. B4.3.11 Emergency Lighting The University has standardised on the bardic range of fittings as specified in Appendix B4.5. Emergency lighting shall be provided from a single point system with a test switch to simulate power failure. Self contained emergency luminaires will remain lit when normal and emergency lighting is required. Generally, exit signs shall have white characters on a green background. Exit signs for lecture theatres shall have green characters on a black background. All exit signs will normally be internally illuminated and remain lit at all times. B4.3.12 Wiring Initial circuits shall have a spare capacity of approximately 50% to allow the connection of additional luminaires in the future. Unswitched active conductors shall terminate in each fitting to allow for future alterations should they occur. B4.3.13 Commissioning and Testing All luminaires installations must be tested and commissioned in accordance with the approved Inspection & Test Plans (ITP) previously submitted by the Contractor (Refer B4.1.7 'Testing & Commissioning of Services'). B4.3.14 Documentation Required Draft tender documents shall be provided to the University in accordance with B4.1.3 'Design Review'. Operation and Maintenance Manuals shall be submitted to the University in a form and sequence outlined in B4.1.10 'Operation & Maintenance Manuals'. Works As Executed Drawings shall be provided to the University in accordance with B4.1.9 'Works As Executed Drawings'.
B4.4 VOICE AND DATA TRANSMISSION B4.4.1 Preamble The Universitys Facilities and Services Division is responsible for on campus management of voice communications network together with block cabling for all telecommunications. Information. Technology Services (ITS) supports Facilities and Services Division with the management of the block cabling supporting the data network whilst being responsible for the installation and maintenance of the data network infrastructure. In addition, ITS provides expertise with the following:
B4.4.2 Standards to Apply All cabling to be supplied and installed shall meet, at a minimum, the following standards: - AS 3000 SAA Wiring Rules; - AS 3080 integrated telecommunications cabling systems for commercial premises; - AS 2032 Installation of UPVC Pipe Systems; - AS 3084 Telecommunications Pathways and Spaces for Commercial Buildings; - AS 3085 Administration of Communications Cabling Systems; - TSB-67 Category 5 Testing.
B4.4.3 Telephone Systems The systems on campus currently comprise the following: Three NEC NEAX 2400 PABX systems located in the Molly Huxley Building that network two satellite sites at Mount Stromlo and Siding Spring Observatories; the Halls of Residence and University Accommodation Services operate Ericsson, Fujitsu and NEC PABXs of varying age and interoperability networked to the main PABXs via tie lines; andThe Affiliated Colleges also operate their own PABX in a similar environment to that outlined above. B4.4.4 Telephone Handsets Generally the allocation of handsets is guided by the following principles: Enhanced digital handsets for Heads of Departments and above with the exception of their Personal Assistants; and Analogue handsets for the remainder of staff and students. The cost of handsets and extension lines at the PABX should be included in the project budget. B4.4.5 Telephone Hardware Outlet Outlets will generally be specified as Category 5 Grade RJ45 to suit UTP cable. The number of outlets required for each project needs to be determined in consultation with the Users. Generally one outlet for each work station with additional outlets for facsimile machines etc shall be specified. B4.4.6 Termination Frames MDFs, IDFs and FDPs shall be specified as Krone or similar. B4.4.7 Permitted Attachments All equipment to be attached to the University telephone system shall be Austel approved and fitted with a label displaying the relevant Austel permit number. Data modems shall not be connected to the University telephone system. B4.4.8 Telephone Cabling Cabling within buildings shall be UTP Cat 5 structured cabling terminated on a RJ45 24 port patch panel in the Communications Cupboard/Cabinet and RJ45 outlet at each work station. Refer to Clause B4.4.12 'Data Network Cabling-UTP Category 5' Underground service cable shall be as specified in the supplementary specification. Refer Clause B4.4.15.
B4.4.9 Communications Room A separate Communications Room shall be provided for each new building. Preferably the room will be on the ground floor and house the telephone MDF, PABX (if applicable), fibre optic termination point, data network communication equipment and the like. Access is for authorised personnel only. Each room shall be supplied with adequate filtered (positive pressure) ventilation or airconditioning. The rooms general illumination level shall be 400 lux and be equipped with additional emergency light fittings. Dedicated cable trays shall radiate out from the Communications Room to access all parts of the building and sized to allow for future additions, but not less that 150 mm. A suitable uninterruptible power supply unit (UPS) may be required to protect critical equipment. All GPOs shall be specified as separate dedicated circuits. Lock dogs shall be installed on circuit breakers protecting critical items of equipment. B4.4.10 Communications Cupboards/Cabinets and Risers Internal service cupboards shall be on each floor together with cable risers extending the full height of the building. The cupboard and riser shall be dedicated to communications cabling and equipment. The minimum internal dimensions of each cupboard shall be 1000 mm W x 800 mm D. Communications cupboards and cabinets shall be provided with a 10 amp double GPO on a dedicated circuit run from the nearest electrical DB. Fit circuit breaker with a lock dog. Cabinets shall be standard 19 inch rack mount, 1800 mm H x 39 RU in height and 675 mm D, complete with steel doors, side panels and vented top and contain a horizontally mounted power rail with ten fully wired 10 amp female three pin outlets and circuit breaker located in the middle and behind each rack with the outlets facing the front of the cabinet. Cabinets have a dedicated 6 mm green/yellow earthing conductor securely fixed to the cabinet frame. B4.4.11 Data Network Cabling Fibre Optic Fibre optic cabling shall be as follows: Multi mode fibre optic cabling: 62.5/125 multi mode fibre optic FDDI grade indoor/outdoor cable Single mode fibre optic cabling: 8/125 multi mode fibre optic FDDI grade indoor/outdoor cable. All fibres shall be terminated using SC terminations and associated duplex through adaptors. Single mode fibres shall be terminated with pre-manufactured pigtails fitted with APC or PC type connectors and fusion spliced onto the incoming fibres and approximately mounted in an approved splice box enclosure. Patch panels shall be an appropriate type of SC fibre patch panel approved by the University and installed to the manufacturers specification. External cables shall be run through existing underground conduits wherever possible leaving a 1m 2 m loop in every pit throughout the length of the cable run. All installed fibres shall be tested in both directions with an ODR. Multi mode fibres shall be tested at 850 um and single mode fibres at 1300 um. All test results shall be included in the Operation and Maintenance (O&M) Manuals. Each cable end and individual fibre pairs shall be labelled with engraved traffolyte (refer to B4.4.13). Where fibre optic cable is installed in Telstra ducts, the cables shall be labelled in each pit to distinguish them from Telstra cables. B4.4.12 Data Network Cabling UTP Category 5 Normal installations shall consist of two (2) category 5 UTP 4 pair cables run from the patch panel and terminated on dual RJ 45 outlets at each work station. The maximum cable distance from patch panel to work station outlet shall not exceed 90 metres. Cables shall be terminated on RJ 45 24 port patch panels in the communications cupboard/cabinet to the following configuration: The 'A' strip shall be closest to the bottom of the rack with the exception where there are telephone tie cables; the telephone extensions will appear on the RJ 45 24 port patch panels located at the bottom of the rack. Ring or loop style cable tidies shall be installed on the first RU then the fourth RU and then every third RU in the communications cupboard/cabinet. Upon completion of the installation, all cables shall be tested and certified to ensure that they are capable of data communications at a maximum rate of 100 MHz. All test results shall be included in the O&M Manuals. B4.4.13 Labelling Generally all labels shall be engraved traffolyte having black letters on a white background affixed with a suitable adhesive or double sided adhesive tape. The labels identifying single mode fibre optic cable shall have red letters on a white background. All work station data and telephone outlets shall be identified with an engraved traffolyte label. Similarly, patch panel labels shall also be engraved traffolyte in a continuous strip with numbers 1-24 inclusive, running horizontally across the panel. Vertical lettering shall comprise engraved traffolyte labels with the letters A-Z inclusive starting at the bottom of the rack. Data and telephone workstation outlets shall be labelled with a letter and number corresponding with the patch panel port, eg B-16.
B4.4.14 Testing Procedures and Commissioning The installation shall be tested and commissioned in accordance with the approved Inspection & Test Plans (ITP) previously submitted by the Contractor. Refer to the provisions of Clause B4.1.7 Testing and Commissioning of Services. All installed cables, connectors, patch leads and components shall be tested with a suitable scanner. Test results shall be included in an O&M Manual as generally described in B4.1.10 Operation & Maintenance Manuals. Works as executed drawings shall be supplied in accordance with the provisions of B4.1.9 'Works as Executed Drawings'. B4.4.15 Supplementary Specification The University has prepared a specification detailing the minimum requirements for network cabling installations on campus, which is available on request or electronically at: http://www.anu.edu.au/facilities/policies/UTPCablingInstallation.html http://netcomms.anu.edu.au/network/specs.html http://netcomms.anu.edu.au/network/cmp.html
B4.5.1 Preamble The appropriate level of security is established at the project design phase. Where major building renovations or building usage changes are intended, provide a security design consistent with the Universitys principles. Refer to sections B4.3 Luminaires and B4.8 Fire Protection and Safety. B4.5.2 Principles of Security Levels The degree of damage, which could be inflicted on the University through personal injury; loss of/or damage to property (including intellectual property); or interruption of a critical service determines the basis for the level of security for buildings, or areas within buildings. Generally, the University prefers to have building perimeters secured electronically, with internal doors locked using a keying system appropriate for the area. Electronic security devices shall be used internally when usage dictates a higher level of security is required. The type and location of any electronic security device shall be subject to discussion with the Universitys Security Manager during the early design stage. B4.5.3 Application to Building Design Design principles having security implications include the following:
B4.5.4 Standards to Apply All relevant SAA Codes shall apply.
B4.5.5 Peripheral Security External lighting shall be provided to all buildings to ensure the main external entrance is well lit and all perimeter doors and other ground floor points of access are properly illuminated. Security lighting from the building shall extend to adjacent carparks and associated illuminated pedestrian path. The building façade shall be designed to minimise recesses, alcoves, columns, etc. that may be a security hazard. Plant room access shall be isolated from the main building security perimeter to ensure that service personnel need not enter secured areas to access the plant room. Main entry doors shall be the principle access for all people entering or leaving the building. Standard doors located on the buildings façade shall be fitted with magnetic locking devices wherever possible. Where reed switches are used, they should detect both door open/closed and lock engaged/disengaged status. Where double doors are installed, the inactive leaf shall be secured with a lockable panic bolt, keyed to the buildings master key system. A suitable door-closing mechanism shall be installed on each active door leaf. Electromechanical doors shall be fitted with the appropriate actuator linked to the electronic access control system. Door actuators shall have the following features: - battery back-up for a minimum of 8 hours in the event of mains power failure. In the event of a power failure, the battery back-up system should keep the doors locked and secure unless there is a fire alarm; - the ability to physically monitor doors when open and closed; - contain a separate electric lock for positive locking; - the ability to monitor the status of the electric lock; - automatic safety reversing of doors; - self-checking safety P.E. Beams; and - after hours access via an electronic control system and manual override. Emergency Exit Doors shall have the following features: - no external door furniture; - all door furniture shall allow for single handed operation; - suitable door closing mechanism; - doors shall be hung to open out; - doors shall be of solid core construction; and - doors shall be secured by either an electronic lock linked to the Fire Alarm and the Divisions central Monitoring Station or a keyed lock keyed to the buildings master key system. Where keyed locks are used, reed switches shall be installed to monitor both door open/closed and lock engaged/disengaged statuss. Electronic access systems shall be fully monitored and programmable to lock/open doors as required by a user defined schedule. Magnetic card swipe readers shall allow access/egress outside normal business hours. B4.5.6 Internal Security The level of security required by the user shall determine the style of security systems used within buildings. Generally, areas shall be zoned according to their security requirements with high security areas grouped together. The principles outlined in Clause B4.5.5 shall be utilised when establishing the security requirements for access to each zone within a building. Additional security devices may be required within specific areas and may include the following:
B4.5.7 Electronic Security Systems & Equipment The University is secured by a CARDAX Electronic Access System consisting of scout controllers located in each building, linked to a series of commander units that are monitored from a central control point in the John Yencken Building. Ancillary equipment, such as passive infrared detectors, electric locks, reed switches, etc., is connected via the appropriate relay to the local scout controller. Commander units are linked to the central monitoring station via dedicated telephone lines. Alarms shall simultaneously communicate direct to the Central Control Station, located in the John Yencken Building, alarm locally at each door and print out on a printer at the Central Control Station. Security intruder alarm systems shall be fully supported by battery back-up for a minimum of 10 hours in the event of normal mains power failure. Security equipment used by the University includes the following: - CARDAX magnetic swipe card readers, CARDAX URI, CARDAX Smart Swipe Fascia Readers. - PADDE ES 2000 electric door strikes, with monitored watch keeper. - Magnetic locks shall be specified as PADDE EML6 for single doors or PADDE EML10 for double doors. -· Break glass release devices shall be specified as (text required) - Reed switches shall be specified as Sentrol flush type 20 or 25mm - Passive infra-red detectors shall be specified as dual technology PIR and microwave - Security panel shall be C/K Sierra type - Batteries shall be EDM BA006 or equivalent - All locks shall be fitted with a diode across the coil to reduce "Back EMF". B4.5.8 Testing and Commissioning The security system shall be fully tested and commissioned to demonstrate to the University that it operates in accordance with the design intent of the Consultant. The Contractor shall be required to produce Inspection and Test Plans (ITP) for the commissioning and testing of the system in accordance with Clause B4.1.7 Testing & Commissioning of Services. All programming at the command centre shall be conducted by the University's Period Contractor. B4.5.9 Documentation Required Draft tender documents shall be submitted to the University for review in accordance with B4.1.3 'Design Review'. Only University approved access control systems and equipment shall be specified and installation shall only be conducted by duly accredited installers. Operations and Maintenance Manuals shall be submitted to the University in a form and sequence outlined in B4.1.10 'Operation & Maintenance Manuals'. Works as Executed Drawings shall be provided to the University in accordance with the requirements of B4.1.9 'Works As Executed Drawings'.
B4.6.1 Preamble The University is committed to energy efficient design and low long-term maintenance costs of mechanical systems. Consultants should be aware of the services available at the commencement of planning. To assist Consultants with the Universitys requirements for the design of mechanical systems, the Division has produced an Air Cooling Policy which may be accessed on the Facilities and Services web page at www.anu.edu.au/facilities/policies. The Divisions technical staff shall also be consulted during the design phase of the project, and Consultants should therefore liaise with the Divisions Project Coordinator. Heating, ventilation and air-conditioning (HVAC) systems are to be designed to ensure a safe and comfortable working environment. B4.6.2 Standards to Apply Fire alarm or protection system shall be designed to operate as per AS1668 and AS1670. All pipe work shall be identified in accordance with AS1345, AS1318 and AS2700. Drift eliminators for cooling towers shall be in accordance with AS3666. Electrical installation shall be in accordance with AS3000 and local authority requirements. Fume cupboards shall be supplied, installed, commissioned, tested and maintained in accordance with AS2243.8. B4.6.3 Electrical Requirements for Mechanical Services Work not covered by local statutory authorities' requirements shall comply with the latest edition of the relevant Australian Standard. Documentation of the proposed electrical installation shall include fully detailed drawings and schematics. Functional schematic diagrams shall illustrate the electrical relationship between: items of equipment; sequence of operation and control of protective functions. Switchboard design shall comply with B4.2.2 'Main Switchboards'; B4.2.3 'Distribution Boards & Control Panels' and B4.2.4. 'Cabinet Construction'. Controls and indicator panels shall comply with B4.7 'Energy Management and Monitoring'; but generally the following shall apply:
Isolation and overload protection shall be provided in accordance with the following: - not more than two power circuits shall be enclosed in the same circuit; - isolating switches shall be provided adjacent to all items of equipment. - contactors, thermal overloads and relays shall be specified as (text required) - each control circuit shall be provided with a properly labelled selector switch offering the choice of manual-off-automatic (refer clause B4.6.10 'Labelling of Equipment'); - short circuit protection may be by HRC fuses or circuit breakers of a capacity in accordance with the manufacturers recommendations; location temperature and operational frequency; - cables shall be selected to ensure that the minimum size of the conductor shall be 2.5mm2 for power and 1.5 mm2 for control wiring using multi-strand copper conductors. (Refer B4.7 'Controls and monitoring' for further specifications of controls wiring). MIMS Cables shall be used for all essential services. Location and cable fixing shall comply with the following: - wiring shall be TPI cables in conduit or on cable trays or TPS or MIMS cables on cable trays; - conductors shall be rated to suit the respective load circuit except where specifically stated; - cables in ceiling spaces shall be run parallel to the structure on cable trays or catenary wires; - wiring within plant rooms and basements shall be surface run but concealed in other areas; - all conductors shall be terminated with an approved clamp or crimp type cable lug except where tunnel type terminals are used; and - switchboards and control cabinets shall be raised a minimum of 1200mm above floor level. Where on-site drilling or cutting occurs within cabinets, filings and swarf shall not be allowed to lodge in electrical components. Cabinets shall be properly cleaned out using vacuum cleaners upon completion of the work. Electric motors shall be 3 Phase built to the relevant international Standard. B4.6.4 Plant Rooms Size plant rooms to accommodate plant and switchboards with sufficient space for accessing and servicing of equipment. Doors shall have sufficient height and width and be positioned to permit removal and replacement of equipment. Vehicular access is essential where bulky equipment such as chillers is placed within the plant room. Allow for lifting equipment to permit plant removal /replacement. The main switchboard and the building management system control panel shall be located in the building's major plant room . Dust and dirt control shall be achieved by the mechanical ventilation system - where installed - keeping plant rooms in a dust free condition. Specify clearly the Mechanical Contractor's responsibility to remove all debris and leave the plant room in a clean condition upon completion of work. Internal finishes to plant rooms shall be as follows: Concrete floors shall be well drained to floor wastes and steel trowel finished. Apply to floors two coats of an approved non slip and chemical and oil spillage resistant floor coating. Galvanise floor drain covers, etc. Protect door openings and floor penetrations by 100mm high bunding; and finish walls and ceilings smooth in a light cream colour with two coats of semi-gloss enamel. Locks to plant room, service shaft and sub-board enclosure doors shall be fitted with Lockwood cylinder, compatible with ANU's standard plant room key. Lighting and power outlets shall be adequate for inspection and repair tasks. Provide a 415V 3 Phase welding outlet in all plantrooms. All equipment, plant and apparatus not factory finished shall be finished painted. Where fully exposed or accessible in plant rooms and other areas, fully paint out piping and other services in their code colours over their entire length. Sheet metal surfaces exposed to weather shall be finished painted after installation, and if applicable, after insulation application. Use weatherproof paint for all weather exposed equipment, plant and apparatus. All exposed hangers, brackets and supports for all services shall be prime coated and finished painted. Provide name plates to all equipment, plant and apparatus in plant rooms and in the field. Labels shall be engraved traffolyte fixed in an approved manner (refer B4.6.10 'Labelling of Equipment). Thermometers, pressure gauge tappings, remote sensing points and valves shall be similarly labelled to indicate their function. A valve schedule shall be provided in each plant room indicating valve number and function
B4.6.5 Heating, Ventilation and Airconditioning Heating and cooling systems shall operate without boilers in summer and chillers in winter. Lecture theatres and other areas likely to be used outside normal hours may need separate heating/cooling systems. Heating, cooling and ventilation plant shall be situated within the building or on the roof. Fresh air may be ducted into plenums but not drawn through plant rooms. Removal of condensate from air receivers and after coolers shall be via automatic traps fitted with manually operated blow down valves positioned for observation of the valve's operation. Requirements for low pressure heating water and chilled water systems shall comply with the following: - individual high spots in any system shall be kept to a minimum; - small collecting pots equipped with automatic air vents and manually operated air bleed cocks shall be located at individual high spots to facilitate air bleeding. The automatic air vent discharge shall be directed to a drain; - air bleed cocks fitted with isolating valves for maintenance shall be located at other high spots; - a suitable water filter and dosing pot of appropriate size shall be fitted into the supply line to the header tank make-up valve to ensure that mud, etc., is prevented from entering the system; - water for both heating and chilled water systems shall be chemically treated at the initial filling; and - system isolating valves shall be installed as appropriate. The Divisions technical staff should be consulted to determine the number and location. Binder engineering twin lock test points for temperature and pressure gauges in water services shall be fitted in the following locations: - inlets and outlets of heat exchange vessels and exchangers; - suction and delivery points of all pumps; and - flow and return headers.
Local Authority Guidelines for the control of Legionnaires Disease must be strictly adhered in cooling tower design, heating and chilled water systems. Cooling towers shall comply with the following: - the location of cooling towers shall be determined together with the Divisions technical staff. Attenuators may be required to reduce potential annoyance to persons in adjacent buildings; - biocide and corrosion inhibitor lines shall be fixed in appropriate locations drift eliminators shall also be included; - a 240V waterproof GPO and hose bib tap, with screw connection for maintenance purposes, shall be located close by and easily accessible; and - disposal of waste water shall be in accordance with the requirements of ACTU. Consideration should be given to engaging the company currently contracted to the University for the treatment of existing cooling towers, boiler and chilled water systems, to carry out the required servicing during the defects liability period. Noise and vibration of air conditioning, ventilation, cooling and exhaust systems shall be designed to ensure that noise levels do not exceed 2dB(A) against the background ambient noise level in areas occupied by personnel. Special attention shall be paid to the elimination of structure borne noise and vibration from equipment, plant rooms, etc.. Details of equipment noise levels shall be recorded during commissioning of the mechanical plant and included in the draft O&M Manual. Service ducts shall be adequate in number and size for the Project. Provision should be made for the reticulation of power, voice/data, outdoor air, exhaust and supply air ducts, water, compressed air and laboratory gases where applicable. Entrance doors to ducts shall be sized and located to facilitate easy entry. Large service ducts shall be fitted with sufficient lighting for inspection or repair work, with light switches located just inside the entry doors. Consideration shall be given to the installation of grid flooring and/or vertical ladders in large vertical risers to facilitate inspection and repairs. Power outlets rated at 240V/10AMP, for use by portable power tools or inspection lamps, shall be located close to entry doors. One small draw wire shall be installed in small horizontal service ducts. Valves for heating and cooling water pipelines shall be specified as (text required).
The University requires the use of Tour & Anderson STAT-D/F balancing valves, where applicable, in water circuits. Boilers shall be gas fired (natural gas) and fully automatic and fitted with on/off or fully modulating burners. Firing programmers shall be specified as (text required) CFC gases shall not be used in any equipment specified. Refrigeration equipment using HCFC and HFC gases shall be subject to approval by the Divisions technical staff. B4.6.6 Fume Exhaust & Fume Cupboards Provide exhaust systems for: toilets, showers, wet and dry photocopier rooms, (where permanently occupied by office staff), darkrooms, tearoom kitchens and other areas as required. Exhaust outlets shall be positioned above roof level and arranged to avoid contamination of air intakes, opening windows, doors, wall vents or other building openings. Where fume cupboards are required, they shall be supplied, installed, tested, commissioned and maintained to the requirements of AS2243.8. Fume cupboards installed in conditioned spaces shall be of variable flow design. The heating and cooling requirements for the conditioned space shall be assessed on the basis of maximum outdoor air for make up, equivalent to the exhaust rate for the fume cupboard with the sash 250mm open from the surface of the workbench. All fume cupboards shall be provided with ventilated under bench cupboards and have adequate space at the sides and front for access to services. Consideration should be given to obtaining fume cupboards from the company currently contracted to the University for the supply and installation of fume cupboards for a new or upgrade program. B4.6.7 Pipe Work and Duct Work The design of pipe work and duct work shall clearly state the necessary requirements to produce the appropriate standard of finish. Due consideration shall be given to material and thickness required; the use of flanges and unions; welding and riveting requirements; spacing of supports; allowance for anchors; expansion loops and bellows; the grading of steam lines or condensation control. All pipe and duct work shall be identified in accordance with the provisions in AS1345 and AS1318.
Flow direction arrows shall be provided on all pipe work. All exposed pipe work and duct work shall be fully finish painted. Colour standards shall be in accordance with the requirements of AS2700.Pipe work and duct work shall be designed to avoid transmission of flow noise to the building structure and occupants (refer Clause 4.6.5 'Heating, Ventilation and Air Cooling'). B4.6.8 Bearings and Drives Bearings requiring lubrication shall be fitted with grease nipples and not painted. Grease nipples, oil filling points and drain plugs shall be easily accessible on all equipment items. Where access is difficult a central lubricating system shall be specified. A lubrication schedule shall be included in the O&M Manual and be on display in each plant room. Belt driven equipment shall have a minimum of two vee belts. Aluminium pulleys shall not be used. Motor mountings, slides or other equipment shall allow simple and accurate belt tensioning; and shall be rigid enough to resist flexing and vibration. Belt, pulley and groove size shall be included in the O&M Manual and belt guards shall be of expanded metal or similar and allow for: easy inspection and removal of belts; sufficient space for maximum belt stretch and tachometer measurement of shaft speeds via circular openings or access panels. Guards shall be strong enough to support the weight of a man and cut away edges of mesh shall be suitably reinforced. B4.6.9 Sump Pumps And Alarms Duplicate pumps shall be provided in stormwater and sewer pits. Each pit shall be controlled by a common control panel with automatic run/stand by/alternating facilities together with multi mode level sensing probes, which shall sense: (1) high level alarm; (3) pump 2 start; (2) pump 1 start; (4) pump 1 and 2 stop. The control panel shall include terminals to provide remote control indication to the University's BAS System for pump operation and high level alarm. A local audible and visual alarm shall also be included in the control panel for high level condition. Pump motors shall be installed to permit disconnection by simple plug withdrawal. Power outlets shall be located a minimum of 600mm above finished floor level. Pumps shall be labelled and labels shall include pump number, circuit number and switchboard location. Refer B4.6.10 'Labelling of Equipment'. Pump and control switches shall be installed to allow easy access for inspection and testing procedures. Where duty and stand by pumps are installed each pump shall be provided with a duty hour run meter. Check valves and isolating valves shall be installed as appropriate. Sumps and submersible pumps shall be designed to facilitate easy pump removal by the provision of adequate lighting and lifting eye above the sump. Submersible pumps and all fittings required for installation shall be specified as being completely corrosion resistant. Non-submersible pump motors shall be located a minimum of 600mm above floor level. Internal and external ground water systems shall be kept separate. The University prefers external sumps and pumps (if required) for ground water disposal and internal sumps for basements, lift wells, etc. Sump pumps shall remain operative when fire alarms function. B4.6.10 Labelling of Equipment All equipment, plant and apparatus shall be identified using engraved traffolyte labels suitably fixedto approval. Labels be black engraved letters/numerals on a white background identifying function, number and, where appropriate, circuit number. All electrical equipment, motors, etc. shall be fitted with rating plates fixed to ensure easy identification. Labelling of control valves, etc. shall be by stamped brass tags identifying valve function and number tied to each valve by wire or chain. All pipes and conduits shall be labelled with adhesive labels showing type of service, direction of flows etc. B4.6.11 Testing and Commissioning Properly designed test points for the measurement of all pressures, flows, temperatures, etc., necessary for the commissioning and performance testing of all equipment shall be provided. Such test points shall form part of the final installation to allow the University to conduct performance checks and fault finding during the operating life of the equipment. The performance of boilers, chillers, cooling towers, etc., is often difficult to establish because of insufficient load and therefore, a testing and commissioning program shall be designed by the Consulting Engineer to ensure that performance can be properly assessed. The specification must clearly state the requirements for testing performance. The Consulting Engineer shall include testing instructions and performance data sheets in the specification for the works. The type of detail required, together with sample sets of test and performance sheets shall be reviewed by the Divisions technical staff before the specification is issued for tendering purposes. The Mechanical Services Contractor shall prepare Inspection and Test Plans (ITPS) for commissioning and testing all plant, equipment, etc., in accordance with the requirements in the specifications and B4.1.7 'Testing and Commissioning of Services'.
B4.6.12 Access To Plant and Equipment Access ladders, walk ways with handrails and catwalks shall be provided where appropriate. Access in the form of duct/plenum access panels shall be provided for all fire dampers, heating and cooling coils, motorised dampers and air filters or filter banks. B4.6.13 Maintenance and Service Spare parts availability and service requirements for capital items of equipment shall be requested in the specification and supplied by tenderers for the works. In particular, tenders for complex and expensive capital items such as turbo chillers should include: - the cost and availability of major spare parts; - the minimum technical expertise required to service complex items of equipment; - availability of adequate drawings & technical information for repairs to be conducted without delay; and - quotation for recommended maintenance program following the end of the defects liability period. The mechanical contractor shall provide adequate training to the Divisions maintenance staff to enable them to maintain the equipment over its service life. Visits by service personnel during the defects liability period shall be strictly controlled as access to plant rooms is restricted to holders of the Universitys plant room key. Service personnel shall contact the Divisions technical staff to arrange access prior to coming on campus. Service reports shall be duly completed and signed off by a member of the Divisions technical staff or an authorised person nominated by the University. A copy of the service report shall be provided to the University. In the event of breakdown emergencies where malfunctioning equipment may cause inconvenience to users or damage to buildings and contents during the defects liability period; the University may, without obligation and without prejudice, make service staff available for emergency work under the following rules: Contractors and Project Managers shall provide the University with out-of-hours phone numbers, and names of persons to be contacted in the event of an emergency. Contractors or Project Managers shall be notified in the first instance that a problem exists and the nature of the problem. If no one can be contacted, the University may, at its discretion, take remedial action and report to the Contractor or Project Manager at the first available opportunity. Depending upon the nature of the Universitys involvement in a breakdown emergency, the University reserves the right to recoup the cost of using its own service personnel. University staff shall exercise care in the performance of their duties, but the University shall not guarantee success or assume responsibility for subsequent faults or consequential damage resulting from failure. B4.6.14 Documentation Required The University requires drawings and specifications in accordance with the provisions outlined in B4.1.3 'Design Review" and B4.1.9 'Works As Executed Drawings'. Operating and maintenance Manuals shall be in accordance with B4.1.10 'Operation and Maintenance Manuals', but specifically shall include: - maintenance schedules for all items of equipment; - a schedule of the settings of all controlling and alarm devices, including the settings of all relief valves; - a schedule of pipe, flange and insulation specifications used for various services; - a schedule showing air-conditioning design air flows and final measured air flows for each air register and major fan together with the final measured air pressure drop across each coil, heat exchanger or filter; - schematic diagrams of the air, chilled water, condenser water and heating water systems showing the manner in which they are designed to operate; the major items of equipment on each circuit; the flow rates; methods of control; measuring and control instruments and their location; - schematic diagrams for natural gas, compressed air, vacuum and other laboratory gases showing pipe sizes, pipe materials, valves and fittings, cylinders (where used) and equipment; - scaled drawings of the plan, elevation and end view for each switch board showing fascia and internal arrangements of meters, lamps, cable busbar chambers, components etc; - make/model number and rating of each electrical component together with the pre and final treatment to the switch board enclosures shall also be included; - wiring diagrams showing power and control schematics, designating cable types and sizes, component makes, model and ratings, wire numbers that tally with those on the BMS drawing; - schematic of inputs and outputs to the BAS; - a schedule of all pressure vessels; - a schedule of filters, including the frequency of cleaning and replacement; and - all Certificates of Compliance. It is the Consulting Engineers responsibility to coordinate and check the recording and supply of data to ensure accurate WAE drawings are produced and supplied to the University. B4.7.1 Preamble The University operates a campus Building Automation System (BAS). Building works involving electrical/mechanical plant shall have controls connected to the BAS. The Universitys BAS is a distributed intelligence open system based on Satchwell BAS 2800+ controls. The University also uses the BAS to monitor consumption of electricity, natural gas and water. Pulse type meters shall be used to measure the consumption of the above with suitable terminals to connect to the BAS. B4.7.2 Standards to Apply AS3000 and AS1431.2 for control switches. B4.7.3 Design Guidelines for BAS Controls The control system (as opposed to the plant alarm system) shall provide to the controller sufficient inputs to both determine whether a device is on or off and also to allow it to select any reasonable and safe configuration of plant. Safety shall not be compromised by the system. Spaces, which are used outside a predetermined schedule or on a 24 hour basis, shall be fitted with motion detectors where feasible. If a motion detector is fitted to AV controls, the output from the detector shall be provided to the BAS. Space temperature sensors shall be fitted in as many zones as are independently controlled by the heating/cooling system. Statuses shall be verified, eg. the status of fans and pumps shall be provided by pressure differential switches not by current sensing relays. All malfunctions shall be detectable by the system and, where feasible, all fault statuses generated by the various devices shall be relayed to the controller. All related plant shall be controlled from the same controller or control system. Sufficient statuses shall be provided to the controller to allow the behaviour of the system to be monitored and diagnosed. Functionality, essential to safe operation, shall be mechanically guaranteed. Control relays shall be designed to prohibit remote controls to cause unsafe sequence of switching. Where plant provides a normal AUTO mode of operation as well as MANUAL ON, MANUAL OFF and BAS, the AUTO position shall be made available on the mechanical services switchboard, using 4-pole switches. Boilers and chillers may be fitted with internal set points for the safe and efficient operation of the device. Where the manufacturer provides external setting of the operating temperature, the setting shall be provided to the controller with appropriate safety measures mechanically incorporated. In general, occupants of spaces shall not be provided with the facility to vary a set point, or turn devices on or off. Where appropriate, occupants may be provided with the capacity to make an input into the system. Where a space is heated or cooled to a predetermined setting, the set point shall be provided to the controller. Outside air dampers shall generally be controlled. Control shall be either open/close or fully modulated. Where a number of devices may be controlled as a set by internal controls, rather than by remote switching of each device in the set, local internal control is preferred. In general, plant and equipment with very small energy consumption and common demand requirements shall be controllable as a group. Generally, an excessive number of statuses that are not independent of others shall not be provided. The condition of Fire Panel Switches, indicating an emergency shutdown of the plant shall be provided to the controller as a status. Controls shall be designed to ensure that the equipment will work safely and without risk to the University staff or property in the event of a loss of power from the controller. The controller shall be programmable to write files to a network drive sufficient to allow the Universitys BAS Supervisor to extract trend log-in data under the control of the Universitys programs. The file structure shall be made transparent to the ANUs BAS Supervisor to ensure that data in University Energy Management Programs can be utilised. Consultants/contractors shall provide a Controls Schematic Diagram to the University for approval by the Divisions technical staff before production of electrical/mechanical diagrams. Refer B4.1.3 'Design Review' B4.7.4 Control Devices All interfacing control devices shall conform to the following requirements: - binary input: voltage free contact, open>1MOHM, closed<100OHM. OPEN = alarm active, CLOSED = device on; - binary output: voltage free contact, CLOSED = device on, OPEN = vital plant on; - analog input: 0-10v, 0-5v high impedance, or 4-20MA constant current, or 1a per K for temperatures; - analog output: 0-10v, impedance >1MOHM; - consumption meters: voltage free OPEN/CLOSE contact pulsing; and - control relays shall operate at 24v.
B4.7.5 Connection to Mechanical Switchboard All control ON/OFF switches shall pass through manual ON/OFF switches mounted on the mechanical switchboard and shall be provided with indicator lamps as follows: - RED = 'ALARM" or device in 'FAULT'; - GREEN = device is switched 'ON' (either manually or remotely); and - BLUE = 'BAS CALL ON' In general controllers should be located beside the main mechanical switchboard which shall supply the necessary power to the controller. All cabling passing through a mechanical switchboard shall conform to the appropriate standards, but the controller shall be limited to extra low voltages (less than 35v) and data cable shall be rated accordingly B4.7.6 Communication Requirements The BAS controller installed in a University building shall be programmable and shall fully communicate with a PC located in the BAS Control Room to allow: - programming of the controller from the BAS Control Room on campus; - receipt of alarm messages (and automatically process & convey them to the Security Station after hours); - view trend data from remote stations and, - perform all the range or user interface functions remotely. Communication between BAS controllers and the BAS Control Room shall be via a copper telephone line and line drivers (supplied by the University) at the controller and the Universitys PABX. It is the Universitys preference that the control system is capable of utilising the existing communication system on campus. As a minimum, provision shall be made for electrical/mechanical interface of a small number of points with existing BAS systems. B4.7.7 Components and Materials The University uses a standard range of control equipment and all new controls shall conform to the Universitys preferred range. A schedule of components and materials recommended by the University is located on the Facilities and Services web page at www.anu.edu.au/facilities/. Orange building wire shall be used for all BAS control wiring. Other wiring shall conform to the requirements in B4.2.5 'Cables'. B4.7.8 Labelling All field equipment shall be labelled with full mnemonic address, out station numbers and point numbers. Labels shall be displayed clearly and will not require the removal of covers, etc. All wiring to field equipment shall be numbered with out station and point number at both ends of the cable and at any junction between the ends of the cable. Refer to B4.2.8 'Labelling'. B4.7.9 Testing and Commissioning Generally all testing and commissioning shall be in accordance with the requirements outlined in B4.1.7 'Testing & Commissioning of Services'. The specialist Controls Contractor shall commission and hand over the system on a point by point basis to the nominated representative from Facilities & Services. The Contractor shall demonstrate all of the software features contained in the specification and shall provide on-site training for the Clients operating personnel for a period of two working days immediately following hand over of the system B4.7.10 MAINTENANCE AND SERVICE (text required) B4.7.11 Documentation Required Tender drawings and specifications shall be provided in accordance with the requirements outlined in B4.1.3. 'Design Review'. Operation and Maintenance Manuals shall be provided in accordance with the requirements outlined in B4.1.10. 'Operation & Maintenance Manuals'. Manuals shall include the following information: - all schematic wiring diagrams associated with the system; - a schedule of all points on the system; - a schedule of all hardware and of all software; - a copy of full technical data associated with the system; - a copy of operators manuals, including operating description of the controls logic; - a copy of commissioning data and a copy of all software; and - full control logic flow diagram.
NOTE: Schematic Logic wiring diagrams will require cable numbers to be indicated. Works as Executed Drawings shall be provided in accordance with the requirements outlined in B4.1.9. 'Works As Executed Drawings'. Warranties shall be provided to the University containing the following: - specification for the Supply of BMS/Controls; and - guarantee that Satchwell will provide support for the BAS 2800 system or its equivalent for a period of 10 years from the hand over date. B4.8 FIRE PROTECTION AND FIRE SAFETY SYSTEMS B4.8.1 Preamble The University prefers automatic sprinkler systems in all new general building types higher than two stories. Should a dispensation from this rule be sought, the application must go to the University Council accompanied by the recommendation of the Fire Commissioner, ACT Fire Brigade and the Director, Facilities and Services. B4.8.2 Interruption of Service Existing services may only be interrupted by prior agreement with the Fire Safety Officer, with interruptions kept to a minimum. During works progress, existing services may require rearrangement for the continuation of works. The contractor when necessary shall allow to re arrange the services as specified including the provision of temporary connections. This may be necessary to ensure that the fire detection coverage is maintained in the building throughout the contract period. B4.8.3 Plans and Approvals The Consultant shall prepare sprinkler system installation contract documents. Such documentation, including plans and specifications are to conform to the Australian Standard for Automatic Sprinkler Installations, AS 2118 as amended, and the requirements outlined in B4.8.5 Additional Requirements. The system is to comply with local authorities' requirements; the Building Code of Australia, and the Fire Commissioner - ACT Fire Brigade. Arrangements are to be made for the connection of the system to the Fire Brigades equipment. The Consultant shall also prepare contract documents for the installation of the fire alarm system as part of the design and documentation procedure. Such plans and specifications shall conform to the Australian Standard for Automatic Fire Alarm installations AS 1670, as amended, and AS 1603.4 supplemented by the requirements outlined in B4.8.5 Additional Requirements. The system shall meet both local Authorities requirements and comply with the requirements of the Fire Commissioner - ACT Fire Brigade. It is the contractor's responsibility to connect the fire system to the University's nominated Fire Monitoring Service Provider via an approved telephone line. The Project Manager/Consultant shall arrange for the successful tenderer to submit full detail drawings of the installation (layout), type of detectors and Fire Indicator Panel type to the Project Coordinator before any work is commenced. Refer to B4.1.3 'Design Review'. The drawings shall show the following information:
- circuit grouping; - detector grouping and position; - route of cabling and conduit runs concealed from view; and - cabling and location of any other ancillary equipment associated with the contract. B4.8.4 Tests Required A performance test shall be conducted for sprinkler systems in accordance with AS 2118, 7.2 and 4.14 . The University requires an endorsed certificate describing the test. Refer also to B4.1.7 'Testing and Commissioning of Services'. For fire alarm systems, it is a requirement that after the installation has been completed the following tests are to be carried out : - every detector, other than fixed temperature, shall be tested in situ by heat; - fixed temperature heads shall be guaranteed by the manufacturer who is also to state the percentage tested in each batch manufactured; and - every circuit shall be tested at the panel. B4.8.5 Additional Requirements For sprinkler systems, provide air cocks at the system's two highest points, as remote from each other as practicable and with waste water pipes to outside the building. The location of air cocks are to be shown on the plans. A Fire Brigade booster connection shall be provided to enable the Fire Brigade to pump water into the system in case of mains pressure failure. The preferred sprinkler head is specified in Appendix B4.8. Drain pipes shall not terminate in blind spaces under the building. Drains will be sized to accommodate a discharge rate of 2,000 litres per minute with 200-250 mm diameter as a minimum. Where required, pressure switches shall be provided to control ventilation fan systems and ventilation damper shut down. The minimum classification of sprinkler systems on the ANU Campus shall be ordinary hazard 1. Extra light hazard systems shall not be accepted. All control valves shall be marked with identification tags and locked in the open or shut position, as necessary, for the installation to be fully operative. All switches and isolators to be clearly labelled. Each installation shall have a tag fixed to the valve set stating the fire Brigade installation number and telephone line number. The specification for the automatic fire alarm system shall include all installation wiring as part of the contract. Such wiring shall comply with SAA Wiring Rules. Switches shall be located at the main fire indicator panel for the purpose of testing and periodic maintenance. The operation of the switch shall bring on a 'flashing light' or other suitable warning system to avoid the possibility of the switch being left in the non-operational position. The system shall operate from mains voltage which is available with battery supply as an emergency power supply only. All detectors shall be identified on the layout plans by circuit and detector numerals. Example: 8/12 indicates No. 8 circuit, No. 12 detector. B4.8.6 Installation of Sprinklers It is the installation contractor's responsibility to ensure the system conforms to AS 2118, as amended. On completion, the contractor shall issue the University with a signed Installer's Certificate prescribed in the above Standard. The installation contractor shall arrange with the University's sprinkler maintenance contractor for the isolation and draining of the fire sprinkler system in the area of the works prior to connection of new pipe work, and for refilling and testing of the system subsequent to completion of the works. All sprinkler systems shall be fitted with an electric pump to enable the sprinkler system to resume operating pressures after maintenance procedures. Retard chambers will not be accepted on the University's fire sprinkler systems. The installation contractor shall pay all costs involved with work carried out by the University's sprinkler maintenance contractor. B4.8.7 Fire Alarm System The system shall automatically indicate an alarm to the local fire authority upon detection of a fire by a thermal or smoke detector or any other fire detection device or manually operated alarm via the University's Fire Monitoring Service Provider. B4.8.8 Fire Indicator Board The Fire Indicator Box shall conform to all requirements of AS 1603.4. The panel shall incorporate all Alarm Zone Facilities (AZF's), Ancillary Control Facilities (ACF's), Master Alarm Facilities (MAF's), indicators and isolators grouped in a neat logical order. The Fire Indicator Box shall also contain all necessary test facilities, batteries and battery charger and battery voltmeter and all associated wiring and accessories. The Fire Indicator Box shall be, recessed, wall mounted and mail box red in colour. The contractor shall ensure that the dimensions of the new Fire Indicator Box enable it to be installed in the void created by the removal of the existing Fire Indicator Box.House the batteries in a separate, ventilated compartment of the alarm panel, completely sealed off from the remainder of the board to prevent corrosion. Stand the batteries on a PVC or other approved corrosion resistant tray of adequate size. The ampere hour capacity shall be sized to allow for additional buzzers, bells, relays etc as required by this specification. Batteries shall comply with AS 1981. The battery charger shall be a fully automatic constant potential type employing all solid state components, and capable of recharging a fully discharged bank of batteries to 80% of their capacity within 24 hours. A warning buzzer shall be provided in the indicator panel and shall operate when the alarm system detects a fire. The buzzer shall be supplied in addition to the buzzer and pilot lights required to give warning of fault conditions. The University requires four spare AZF's be supplied, the remaining unused sectors shall be covered with suitable blanking plates. All used AZFís shall have their end of line resistors terminated in a terminal strip in the board. Provide the following controls in the Fire Indicator Box: A manually operated switch to isolate: - door holders; - bells and relays for the purpose of -maintenance; - ir conditioning shutdown; and - isolate paging/evacuation system. All switches shall be clearly labelled. B4.8.9 Detectors All thermal detectors shall comply with the requirements of AS 1603.1 unless otherwise specified. They shall be type A normal temperature compensated type that operate as slow or rapid rates of temperature rise. They shall be of Wormald's or the Hochiki type. The number of detectors per zone shall be a maximum 85% of that allowed in AS 1670. All detectors containing end of line resistors shall be clearly marked on their bases. All ceiling mounted detectors shall be symmetrically located with respect to luminaries, air registers, walls etc. Gas detectors shall comply with relevant Australian Standards and shall also be installed symmetrically in relation to other fixtures. Smoke detectors shall comply with AS 1603.3 and shall be of the Hochiki type. B4.8.10 Wiring methods All wiring shall be installed so to be readily renewed, repaired or relocated without affecting building finishes and construction. Wiring shall conform to all relevant requirements of AS 3000. All cables shall be: - adequately fixed and supported with purpose made clips, cleats or saddles; - installed to permit adequate air circulation around each cable; - installed between equipment without any joints; and - installed on the loop in, loop out principle without the use of connections for sub-circuit wiring, no star point wiring configurations will be accepted. All conduits shall be: - installed using the loop-in system; - 20 mm minimum diameter, oval conduits are unacceptable; and - be concealed from view by running in ceiling spaces, concrete slabs or chased into rendered masonry walls unless specified or agreed by the University. Conduit exposed to view shall: be installed in straight runs which are parallel or normal to the building structure over routes agreed to by the University. B4.8.11 Labelling And Cable Markers All wiring to detectors, door holders, door locks, bells, sirens mimic panels shall be clearly marked. Marking shall be done with Grafoplast markers. The following schedule shall be adopted:
- All other ancillary equipment shall be marked as follows: (text required) B4.8.12 Labelling All switches and isolators shall be clearly labelled. The Fire Indicator Box shall have a label fixed to the front of the panel stating the following: - fire Brigade installation number; - telstra line number; and - source of 240V power supply (distribution board and circuit number). Labels shall be of black background with white engraved letters. Refer to Clause B4.2.8 'Labelling'. B4.8.12 Compliance of Installation The installation contractor is responsible for ensuring the system conforms to AS 1670 and to AS 1603.4 both as amended. On completion, the contractor shall issue to the University a signed installer's certificate as prescribed in AS 1670. A copy of the certificate shall also be provided to the ACT Fire Brigade. B4.8.13 Hydraulic Hose Reels and Fire Extinguishers The size and length of hoses are determined by the Fire Commissioner - ACT Fire Brigade. The hose nozzle shall be chromium plated brass with positive rotation manual shut-off control. Fire extinguishers shall be provided in accordance with the requirements of the Fire Commissioner - ACT Fire Brigade. Fire extinguishers shall comply with the relevant Australian Standards. Installation of hose reels shall be included in the fire services contract not part of the general building works. B4.8.14 Exit Doors All exit doors shall be fitted with an approved latching device capable of opening from inside with normal door lever/knob action and without recourse to a key. Should dead-locking devices be used, the dead-lock must cancel out under normal door lever action. B4.8.15 Fire Doors All fire doors shall be approved self-closing type, having an appropriate IFR rating as required by the Building Code of Australia. All fire doors shall comply with Australian Standard AS 1905 Part. The manufacturer's name and trade name/mark by which the door type is identified, and also the year of manufacture and fire resistive rating shall be indicated by a metal tag secured to the door and door frame. Handles shall be provided on both sides of the door and under no circumstances is a non-approved locking device to be used. Sliding type fire doors shall not be installed, expect in special cases and then only by approval of the Fire Commissioner - ACT Fire Brigade. B4.8.16 Smoke Doors Corridor smoke doors shall be double acting with a 180 degree swinging movement. The doors shall be effectively sealed against fire and smoke for reasonable periods of times. The closing mechanism shall ensure that the door returns to the sealed position as required. B4.8.17 Electromagnetic Door Holders All smoke and fire doors shall be fitted with magnetic door holders operating in conjunction with the fire protection or detection system, whichever is the case and shall operate on 24v dc. B4.8.18 Emergency Lighting Emergency lighting shall be installed in accordance with AS 2293 Part 1 and AS 3000 requirements. Types of fittings to be of Bardic type as specified in Appendix B4.8 'Fire Service Equipment'.
B4.8.19 Fume Cupboards Exhaust fan shut-downs shall be connected to the fire alarm system. Fume cupboards shall be provided with a sprinkler head in a fully sprinkled building or thermal detectors in a building equipped with thermal fire detectors in accordance with AS 2243.8 1986 as amended. B4.8.20 Evacuation Systems Evacuation systems shall be installed in all buildings that are greater than two stories high. All evacuation systems installed shall comply with AS 2220 and Building Code of Australia requirements. Where required, the contractor shall ensure that the location of Warden Intercom points can be operated without interference from noise from the system speakers or air handling system. B4.8.21 Evacuation Training Prior to handover,the Fire Services Contractor, shall ensure that the ANU Fire Safety Officer has been briefed in the operation of the various fire safety systems under the Contract. When completed, the ANU Fire Safety Officer shall arrange for the emergency evacuation training of the building occupants as required. B4.8.22 Documentation Required Draft tender documents shall be provided to the University in accordance with B4.1.3 'Design Review'. Operation and Maintenance Manuals shall be submitted to the University in a form and sequence outlined in B4.1.10 'Operation and Maintenance Manuals'. Works as Executed Drawings shall be provided to the University in accordance with the requirements of B4.1.9 'Works as Executed Drawings'. All Compliance Certificates required by the local Authorities shall be provided to the University and bound into the O&M Manuals.
B4.9 ENERGY CONSERVATION & MANAGEMENT B4.9.1 Preamble The University recognises energy conservation and management as a significant element of life cycle costing of new and existing buildings. It is important that an efficient use of energy is accomplished through effective building design. Accordingly, all factors influencing energy consumption shall be considered throughout the design stage. B4.9.2 General Principles and Guidelines When considering use and occupation of buildings, it is desirable that the interface between different user groups, activities and zones within buildings be limited. Where feasible, areas with expected similar energy requirements are to be grouped together. Where multiple unrelated users occupy buildings, the University requires that energy consumption of each group shall be individually monitored. To optimise internal environmental conditions, the following shall be considered: - mechanical ventilation to comply with AS1668. Consider all natural ventilation possibilities; - generally, the University is committed to air-conditioning the buildings to provide a safe and comfortable work environment. However, other energy efficient systems that satisfy the above goals shall be considered if able to meet the Universitys OH & S Guidelines for human comfort; - humidity control shall only be provided for specific experimental or storage purposes; - task lighting shall be used wherever practical rather than overall illumination techniques that may require an unnecessarily high level of illumination; - building automation systems (BAS) as described in Section B4.7 'Monitoring and Controls', are used in all University buildings which allows: 1 operation of building plant to be monitored and controlled in each building; 2 plant operation viewing from a central control station and any adjustment of control systems implemented from there;
3 alarm messages transmission to the central control station when the BAS detects a malfunction. The system stores historical data on the PC located in the central control station for diagnostic, energy billing and design purposes; - new plant/controls installed in existing/new buildings shall be suitable for connection to the BAS; - electricity and gas tariffs have been negotiated by the University with the local supply authorities. Consultants should check with the Divisions technical staff when preparing energy consumption or life cycle costing analyses. B4.9.3 Environmental and Architectural Considerations Building form shall be in accordance with the principles outlined in Sections B1 and B3. Organise the efficient use of circulation space and zoning to minimise overall building volume(s). The effects of shape, mass and orientation shall be considered in developing a thermally efficient building design. Roof spaces and walls of buildings shall have adequate thermal resistance to heat loss/gain. The design and position of glazed fenestrations shall ensure that the need for natural light and ventilation is weighed against solar and thermal loads. Demonstrate adequate consideration of the following: - sun control techniques (including sun shades and glare control); - maximum use of natural light and ventilation; and
Internal or glass applied films and sun control measures, shall not be used unless external measures cannot be applied. Internal wall finishes shall be in accordance with the recommendations outlined in AS1680.1 (Section 6) regarding the reflectance of surfaces. Task areas shall be protected from all sources of glare with particular attention being given to areas where personal computers are to be located. B4.9.4 Mechanical Services and Equipment Energy targets shall be established for new buildings to provide a measure of energy efficiency for the design and the impact of any special requirements outlined in the project brief. Such targets will then be used to assess the achievement of energy efficiency in subsequent operation.
When determining the size of plant to be installed, consideration must be given to: - using double glazing for windows to reduce thermal loads on the building; - the availability of power; - the provision of modular plant for flexibility in meeting seasonal changes and changing use patterns; and - thermal storage and heat recovery systems. Ventilation fan power consumption shall be minimised by: - designing ducting and equipment for low static resistance to ensure low fan pressure; - using variable air flow volume to reduce fan power at part load; - selecting the fan and drive train for high efficiency; and - using efficient means to vary fan performance to suit variable air volume (VAV) system. Pumps shall be specified to: - operate at the highest efficiency point avoiding the use of undersized piping systems; and - include consideration of sequenced steps or modulations of pumping capacity for economy. Evaporative cooling is energy efficient when large quantities of air are cooled and the relative humidity is low. Systems integrating both evaporative cooling and heating are not generally energy efficient and incur high maintenance costs and, accordingly, are not favoured except for applications such as green houses, workshops and the like. Where it is necessary to use refrigeration for cooling an economy cooling cycle, utilising up to 100% outside air (when conditions are favourable), shall be used. The use of sprayed cooling coils shall be considered (in conjunction with the economy cycle) to reduce refrigeration and re-heat requirements. Refrigeration plant shall be selected for economical part load operation. With multiple refrigeration equipment, various combinations of capacities shall be plotted against anticipated running costs to determine the most economic configurations whilst not compromising the systems performance, particularly at low system load. Where possible, the heat rejection from the refrigeration system shall be used for heating purposes. Radiant heating generally requires less energy than warm air heating. Heating hot water boilers shall not be used in domestic hot water systems. Hot water supply temperature used for heating shall be as low as practical to reduce system losses, but not to the point where it may effect boiler operation efficiency and life. Thermal storage may be used to store heat for re-use to reduce capacity and maximum demand. Waste heat recovery from exhaust air or gas, condenser water, etc. should be considered. Where it is necessary to condition large quantities of air for laboratories or special areas, air-to-air heat recovery devices shall be considered as a means of reducing plant capacity and running costs. Appropriate plant controls shall be selected to prevent excessive energy consumption. Refer to Section B4.7 'Controls & Monitoring' for details of the Universitys requirements. Consultants, Project managers and Contractors shall consider the 'maintainability' of the plant. Ease of access to components requiring scheduled maintenance facilitates better maintenance procedures thus preventing excessive energy consumption by poorly maintained plant. Domestic hot water services shall be selected to ensure that the balance between energy source, location and long term running costs is properly evaluated. To ensure the most efficient operation of the hot water unit standing heat losses through long pipeline runs shall be avoided. Gas fired units shall be selected in preference to electric units and all heating pipe work shall be lagged. Stairwells should be designed and positioned to encourage use for vertical circulation in preference to lifts. B4.9.5 Management of Lighting The goal in the management of lighting is to gain maximum benefit from the system whilst minimising wasted energy. Consultants shall calculate installed lighting loads and submit these to the University for consideration as part of the design review process refer B4.1.3 'Design Review'. Design guidelines for lighting are set out in Section B4.3 'Luminaires'. Building lighting shall: - enable tasks to be performed quickly accurately and easily; - allow building occupants to work and move about in the building in safety; and - achieve the desired character of the interior. Lighting levels shall reflect a practical application of the requirements of the current issue of AS1680 to provide a safe, visually comfortable, working environment.
Lamp selection shall be made following consideration of the following: - colour rendition; - lamp lumen depreciation; - lamp shape; - strike/restart time; - ease of lamp removal for changing; and - lamp life and cost. Tungsten lamps may sometimes be suitable whereby careful light control and a high utilisation can be achieved. Fluorescent tubes are the preferred light source and the University has standardised on 36-Watt and 18-Watt units. Fixture selection shall be made after the following have been considered: - the efficiency of a fixture in space (co-efficient of utilisation); - the importance of having as low glare system in areas such as terraced lecture theatres, etc. (visual comfort probability); - resistance to dirt build up (luminaire dirt depreciation - LDD); - low glare diffusers should be used with acrylic prismatic lenses for fluorescent fittings. Opal diffusers shall not be used; - the recommendations of AS1680.1 regarding the minimum shielding angle of luminaires shall be followed where screen based equipment is used; and - the use of heat removal of air handling fixtures may permit the use of smaller more efficient cooling systems to maintain comfort levels. Minimisation of energy consumption shall be considered taking the following into account: - the balance between task and building illuminance; - availability of daylight lighting; - provision of switching controls to enable lighting to respond to daylight variations and room occupancy; - use and maintenance of high surface reflectances; - mounting height of luminaires; - appropriateness of fittings related to use; and - efficient exterior lighting. B4.9.6 Documentation Required To ensure that consultants are aware of the various factors that lead to significant improvements in energy performance, an Energy Evaluation Statement shall be completed when documentation is complete. The statement enables the University to review predicted energy use and to initiate recording, budgetary and energy operations throughout the building life. A proforma of the Energy Evaluation is included in Appendix B4.6. PART B REFERENCE MATERIAL B4.10 LIFTS AND TRANSPORTATION SYSTEMS B4.10.1 Preamble In multi-level buildings, lifts are an essential contributor to building accessibility and vertical circulation. Lifts provide occupants with a link from entrance levels to other levels and facilities within a building. Accordingly, lifts and their controls should be designed to cater for a wide cross-section of the community, including persons with disabilities. Lifts should meet the following demands: - be large enough to accommodate wheelchairs, stretchers, etc; - have controls that can be readily understood and accessible by all users; - have audible and / or tactile assistance; - allow all users independence in being able to access an entire building; and - have ready access to safety equipment. Consultants should also refer to Section B3.7 'Access and Facilities for Persons with Disabilities' for further details of requirements for persons with disabilities. B4.10.2 Standards to apply The following Australian Standards are deemed to be applicable to lift installations: - AS 1735 - Australian Lift code; - AS 1428 - Access for Persons with Disabilities; - AS 3000 - Australian Wiring Code; and - AS 1657 - Fixed Platforms, Walkways, Stairways and Ladders,
B4.10.3 Application of Lift Types The use of individual platform lifts or stair climbing devices may substitute for a full passenger lift, but their use shall be considered with discretion. Fully automatic, enclosed lifts are the best mode of vertical transport for all persons. Instances where individual appliances may be of particular benefit include the following: - when the travel distance between levels is not excessive; - when the installation of a fully complying lift would be impracticable due to the nature of the space being accessed; or - where constraints within the existing building limit options for access by other means. The choice of lift or appliance shall be made with reference to the table in Appendix B4.7 'Application of Lift Types'. B4.10.4 Lift Machine Room The design of lift machine rooms shall comply with the following: - the room size and location must allow easy access to the space and its equipment; - lighting, GPO's and ventilation to comply with AS1735 & authority regulations; - in cases of hydraulic lifts provide appropriately sized oil coolers; - the room door to swing out and be fitted with a closer complying with AS1735; - the room door shall be two hour fire rated; - fit the room door with a night latch type lock allowing exit at all times; - fit a Lockwood cylinder compatible with ANU's standard plant room key; - supply fire extinguishers or sprinkler system complying with AS1735; - walls, floor and ceiling shall be finished full gloss enamel for ease of cleaning; - the preferred ceiling colour shall be white and the walls off-white; - floors shall be sealed and finished two coat grey nonslip paving paint;
- control and hoisting equipment shall be well lit with twin 36 watt fluorescent reflector type fittings incorporating a safety guard. Lighting to be positioned to ensure that maintenance staff are not working in their own shadow. Emergency lighting shall illuminate control gear. B4.10.5 Lift shafts All lift shafts for electro-hydraulic and electric automatic lifts shall be of masonry construction unless otherwise specified by the lift manufacturer. Shafts for other vertical transport devices, if required, shall comply with the manufacturer's specifications. Sumps and flush covers to lift pits shall comply with AS1735 and local regulations. Refer B4.6.9 'Pumps and Alarms'. Ventilate lift shafts and fit a fire protection system complying with AS1735 and local regulations. B4.10.6 Lift Cars The internal dimensions of a lift car should not be less than 1100mm deep x 1000mm wide. An increase in width to 1580mm (+) is preferred to allow the necessary space for wheelchair circulation. All dimensions are free of handrails. Handrails to assist passenger stability shall be provided on the sides and rear wall at a height of 800-950 above the floor. Handrails must not impede circulation or lift controls. Handrails facing a doorway must be returned to the wall, or abut a return to the side of the door. Design considerations of floor surfaces in lifts should be similar to those of corridors. The threshold of the lift should allow an even transition from lobby to lift car. The lift car shall be automatically self-level bringing the car floor to each landing within a tolerance of 12mm from each direction of travel with car fully loaded to capacity or empty. Lift car lighting shall be 36-watt low brightness fluorescent type. The design and make of all fittings shall ensure quick and easy replacement of tubes. Emergency lighting shall be provided. A 180mm-diameter exhaust fan shall be installed in the ceiling of the lift car. Lift and counterweight guides shall be the self-lubricating roller-type. B4.10.7 Doors, Frames and Indicators Lift doors shall be horizontally sliding, centre parting, power operated and fully automatic. Ensure passenger protection systems are fitted in conjunction with doors, including safety shoes on the door edge and infra red beam devices. The door re-open system should not rely upon contact between the closing door and an obstruction. Upon failure of the passenger protection system, the doors shall remain open for at least 60 seconds unless overridden by the door close button, and an audible alarm shall be sounded in the car upon door closure. The lift door shall provide a minimum unobstructed clearance of 880mm in width to allow wheelchair access. The minimum landing width shall be 1350 to allow manoeuvrability of wheelchairs. All indicating lights shall be of long life led dot matrix type. At least one international symbol for access and a further symbol for call buttons shall identify a lift accessible for persons with disabilities. Landing call buttons shall be mounted adjacent to the lift entrance with the 'up' button uppermost and shall be vandal resistant. Buttons shall be not less than 19mm in their smallest dimension. There shall be visible and preferably audible signals to indicate that the call has been registered and when the call has been answered. Illuminated and audible signals also denotes the direction of travel of the arriving lift car, eg one tone for an upward direction and two tones for a downward direction. B4.10.8 Controls Lift car control panels shall have a common design and layout for all lifts and be hinged for maintenance purposes. There shall be a common theme for the designating of floor levels. Such designation will be in accordance with the University's signage protocol (Refer B3.6.16 'Internal signs and Directories'). Lift car control panels shall be positioned for accessibility to people in wheel chairs. All control functions, including car position indicators, shall be on a single panel in a single location or duplicated if the floor area of the lift car is less than 2.72m2 The control panel should be positioned either side of the door or both if required. Control buttons shall be suitable for people with disabilities and shall be located in a zone 700-1250 above the lift car floor. The control panel shall contain an exclusive key switch regulating on, off and park functions. B4.10.9 Emergency Communications and Alarms Emergency communication is essential in lifts, particularly for people with disabilities. It is essential there is a direct two-way communication between the lift and the University's 24 hour manned Security Station. Emergency communication equipment shall be identifiable by, visual, audible and tactile means. B4.10.10 Commissioning and Testing The local regulatory authority conducts lift inspections to ensure that the installation complies with all requirements of AS1735. Should the lift initially be commissioned as a builder's lift, it is required to undergo a second inspection prior to hand over. The Project Manager or contractor shall be responsible for protection of the lift and any making good prior to practical completion. The University requires Inspection and Test Plans be submitted for approval prior to the commencement of commissioning and testing procedures (Refer B4.1.7). Upon practical completion, the installation shall be handed over to the University complete with all software and hardware to ensure safe operation. All equipment shall remain in place during and after the expiration of the Defects Liability Period, regardless of the outcome of any continuing long-term maintenance agreement. B4.10.11 Maintenance and Service Tender documentation must state a maintenance period for lift installations of twelve months from the date of practical completion. Also, as part of tendering there shall be a requirement to submit separate prices for Twelve Monthly Periods of comprehensive maintenance based on fortnightly visits. The contract documents shall allow for the contractor to meet with the Division's technical staff upon completion of the installation for instruction on the lift's use and its maintenance. A period not less than one working day shall be allowed. B4.10.12 Documentation Required Draft tender documentation shall be provided to the University in accordance with: B4.1.3 'Design Review'. Operation and Maintenance Manuals shall be submitted to the University in a form and sequence outlined in B4.1.10 'Operation and Maintenance Manuals'. Works As Executed Drawings shall be provided to the University in accordance with the requirements of B4.1.9 'Works as executed Drawings'. All Certificates of compliance as required by the local authorities shall be submitted to the University and bound into the O&M Manuals.
B4.11 HYDRAULIC AND IRRIGATION B4.11.1 Preamble The University is responsible for the inground infrastructure on campus, some areas of which are now old. Consultants should be aware of the need to fully evaluate the impact that any new development may have on the existing reticulation system. Whilst evaluating the capacity and condition of existing services, consultants shall confer with the Divisions technical staff, (Manager, University Maintenance), who will be required to sign-off the proposal at an early stage. The scope of hydraulic services shall comprise: - incoming water supply and tappings (exclusive fire services, refer Section B4.8); - domestic cold water supply reticulation; - flusher service reticulation or cistern toilets; - sanitary plumbing, drainage and fixtures; and - stormwater drainage. B4.11.2 Standards to Apply All sanitary drainage and plumbing installations shall be subject to local authority's regulations. B4.11.3 Design Criteria Sanitary plumbing, drainage and fixtures shall be subject to the following: - no toilets or waste facilities shall be provided below the level of the main sewer lines; - dry floor wastes shall be provided with solenoid activated self flushing mechanisms to meet local authority requirements; and - selection of fixtures and fittings, including limit water usage devices, should take account of availability and continuity of spare parts supply.
Stormwater drainage systems shall be subject to the following: - the system shall be designed in accordance with the CSIRO recommendation for a 100-year return rainfall intensity with drainage gravitating to appropriate stormwater drains. Consultants shall provide the University with calculations demonstrating the adequacy (or otherwise) of the existing drainage system relating to its capacity to cope with the proposed new stormwater load; - all sumps and inspection pits shall have a silt chamber below the lowest invert level; - shoes of downpipes shall not be mortared in place, but shall discharge into a separate trap with grating. The trap will be designed to minimise splashing at the downpipe discharge point; - rainwater heads shall be readily accessible and shall have adequate overflow capacity; - box gutters shall be avoided; and - gutters shall be designed to minimise the build up of vegetable detritus. Consultants are encouraged to discuss the Universitys requirements with the Divisions technical and maintenance staff early in the design phase. Refer B4.1.3 'Design Review'. B4.11.4 Isolating Valves And Stop Cocks All spurs off campus mains for water and gas supply to buildings shall be fitted with isolating valves. In the case where a building is supplied by a ring main, the main shall be capable of being isolated on either side of the tee-off position. Stop cocks in hot and cold waterlines and gas services shall be easily accessible and clearly marked. Separate stopcocks are required for each floor and for each laboratory on each floor of a building. Backflow prevention devices required by the local authority shall be installed in an easily accessible position. Where an irrigation system is not installed, stopcocks or quick coupling devices shall be provided on the perimeter of the building for irrigation purposes. All sanitary fittings, cisterns, hand basins, sinks etc. shall be fitted with isolating valves to the hot and cold water supply.
B4.11.5 Metering All incoming cold water and gas services shall be metered. Meters shall be readily accessible and in accordance with the requirements outlined in Section B4.7 'Controls and Monitoring'. B4.11.6 Domestic Hot Water Units Electric or natural gas hot water heaters are used on campus. Electrically operated hot water units shall not have automatic release buttons that operate when there is a power failure. Gas fired hot water units shall be positioned in an area that is well-ventilated and not subject to negative pressure or strong draughts. Working temperature settings shall be in accordance with the BOMA guidelines. Hot water units shall be positioned in a readily accessible position for ease of maintenance. B4.11.7 Cisterns and Flushing Valves The use of exposed half flush cisterns is preferred in buildings solely occupied by University staff, or combination of staff and research personnel. Recessed cisterns shall be used wherever undergraduate use occurs. Flushing valves are preferred where toilets are subject to peak usage, eg. toilets adjacent to a lecture theatre or a large teaching laboratory. If flushing valves are installed, consideration shall be given to providing ease of access for maintenance purposes and sound attenuation. B4.11.8 Neutralising Chambers Consultants shall determine the type, quantities and concentration / dilution levels of chemicals to be discharged into the sanitary drainage system. Users must provide accurate information to assist consultants in determining the need for a neutralising chamber. The local water supply and drainage authority shall also be consulted regarding their requirements. If a neutralising chamber is required, it shall be located to provide easy vehicular access where pumping out or cleaning procedures are necessary. Neutralising chambers shall not be located in plant rooms. Associated dosing tanks shall be located where maintenance staff can gain access independently of any laboratory or office area. An adjacent cold water supply and general purpose outlet shall be provided for mixing purposes. Ventilation of neutralising chambers shall be such that any fumes do not re-enter the building. B4.11.9 Colour Coding Plumbing, electrical and mechanical subcontractors shall colour-code their services for identification.
B4.11.10 Stormwater Reticulation Consultants shall ensure that the entire stormwater reticulation system has ample capacity to cope with intense storms over a short period. Consultants shall check the existing stormwater mains to which a new building is to be connected to ensure that they are serviceable and in the correct location. Gutters, downpipes and discharge sumps shall be designed to minimise the likelihood or blockage caused by vegetable detritus. Refer also to B3.5.3 'Roof Drainage'. B4.11.11 Irrigation It is preferred that the landscape forming part of each project be suitably irrigated as determined by plant species. Where an irrigation system is required, the installation shall form part of the project and be adequately documented. Irrigation systems shall be separately metered and shall not form part of the cold water supply for a particular building. The University prefers that electronic control devices control irrigation systems. The issue of a centralised control system is currently under review by the University; therefore, consultants should discuss the matter with the Divisions technical staff. B4.11.12 Testing and Commissioning Generally, all testing and commissioning shall be in accordance with the requirements outlined in B4.1.7 'Testing and Commissioning of Services'. B4.11.13 Maintenance and Service Consultants should note that the specification shall require the contractor to meet the Divisions technical staff upon completion of the installation for suitable instruction regarding maintenance and servicing of the installation. B4.11.14 Documentation Required Consultants shall submit their calculations on the adequacy of the stormwater drainage system to the University for acceptance early in the design phase of the project. Draft tender documents shall be provided to the University in accordance with B4.1.3 'Design Review'. Operation and Maintenance Manuals shall be submitted to the University in a form and sequence outlined in B4.1.10 'Operation and Maintenance Manuals'. Works as Executed Drawings shall be provided to the University in accordance with the requirements of Clause B4.1.9 'Works As Executed Drawings'. All Certificates of Compliance shall be submitted to the University and bound into the O&M Manuals
|